products-hero_1920x1440

Power Plant Commissioning

The power plant commissioning process takes account of all elements of the Design and Functional Specifications to ensure all elements of the system operate as designed, and interface with the entire system completely.

Whether the Scope of Supply includes a single generating unit, combined heat and power (CHP) plant or a full turnkey project, our Commissioning Team is responsible for the commissioning and setting into safe operation all equipment and services supplied as per the Scope of Supply.

peaking-plants-benefits_1920x1440

We work closely with the suppliers of ancillary equipment to ensure:

  • All equipment supplied meets the relevant specification
  • Any suppliers completing Installation and Commissioning works demonstrate that such works can and is completed to the highest standards
  • All equipment is installed correctly
  • All individual equipment or elements of any system operate as designed and required
  • All supplied equipment interfaces correctly with both the Edina Systems and the complete site systems as required

Dependent upon the Edina Scope of Supply the Commissioning Process normally falls into these key areas.

Pre-Energisation Commissioning

Many pieces of equipment or services are tested to ensure that energisation of a building or system can take place safely.

These include:

  • Electrical transformers, cabling and switchgear – Correctly installed, inspected and tested appropriately before being made ‘live’
  • Pipeline Systems – Correctly installed, cleaned and tested before being filled with operating medium
  • Fire, Gas, and Security systems – Correctly installed, inspected and tested appropriately to ensure that they offer the relevant protection when required

Dry or Static Commissioning

Commissioning of the generating unit or CHP plant is completed to ensure that all systems are safe to energise and are completed before the unit is started.

These include:

  • All relevant and required pre-running checks and set up procedures as determined by the generating unit manufacturer are completed
  • Complete static inspection of the installed systems, including all oil, gas and cooling systems
  • Complete testing of all PLC Programming and Binary and Analog I/O
  • Static testing of the alternator / generator unit
  • Static Testing of GCB Or HV Switchgear, Interfacing and controls
  • Testing of all valves & controls including operation and strategy
  • Testing of all installed safety systems

Additionally, throughout this stage all systems and equipment external to the generating unit or CHP plant is inspected and tested to ensure all systems are safe to enter operation.

This includes:

  • Pre Heating Systems – checked and tested, to ensure the installation meets all regulatory, design and safety criteria
  • Building Ventilation Systems – tested to ensure correct operation at the relevant times and that all safety interlocks are operational
  • Gas Systems – all installed gas systems and equipment is tested in accordance with regulatory requirements
  • Bulk Oil Supply Systems – installed correctly, tank level gauges and alarms operational
  • Waste Heat Recovery Systems – Boiler or Heat Exchanger – installed correctly, complete relevant pressure testing, ensure all safety systems tested, ensure associated control systems operate correctly

Wet / Live or On Load Commissioning

The generating unit or CHP plant is started and all checks relevant to safe operation and synchronisation of the unit against the electrical grid are carried out to include:

  • Initial Start / Stop Tests
  • Verification of all protection elements and settings
  • Initial synchronisation checks, to ensure the generator aligns with the electrical grid
  • G99 / G10 (Mains Protection Tests) to Distribution Network Official satisfaction

Once the generating unit or CHP plant is capable of grid synchronisation, it is brought up in load stages according to recommendations set by MWM and Edina. The load stages are carried out in isolation from any site system to ensure the generating unit or CHP plant can attain full load capability.

During this process and at each load step, the engine, alternator and system pressures, temperatures, exhaust emissions and performance is checked with calibrated equipment and the results are recorded and verified against stated performance criteria.

The generating unit or CHP plant is then ‘opened up’ to the sites systems. At this stage, the performance and output of the unit is checked against agreed performance criteria, thermally and electrically, and any adjustments or trimming of the control systems is carried out. This includes a period of ‘normal’ operation against all site systems.

Once complete, the generating unit or CHP plant is subjected to an internal ‘trial’ performance test to ensure that all Contractual Performance criteria is met, including:

  • Electrical & Thermal Output Efficiencies
  • Gas Usage
  • Noise Specifications
  • Exhaust Emissions
  • Reliability over a pre-determined period
  • Start-up & Load Ramp Tests
  • Hot & Cold Start Capability Tests

Performance Testing

In accordance with Contract Conditions in place, the generating unit or CHP plant is then subjected to the agreed Performance Tests. These would normally replicate the ‘Trial’ tests completed. The timing and duration may vary according to the individual customer requirements.

Project Handover

Providing all the necessary tests and inspections have been passed satisfactorily, the generating unit is ready to enter commercial operation. This may initially be in the form of an extended reliability test period, e.g. 28 days.

At the time of Handover to the End User, the Commissioning Team will complete the Operator familiarisation Training, the purpose of this is to, familiarise Site Staff and Operators in the Safe, Routine Operation of the Edina Supplied Equipment installed.

This includes:

  • Plant components and layout
  • Electrical Schematics & P&ID’s
  • Interface with client systems
  • Pre start checks
  • Start, stop, load change
  • Manual and automatic control
  • Fault recognition & diagnosis via TEM and ComAp systems
  • Emergency stop & Protection systems (electrical, mechanical)
  • Isolation of plant ancillaries (electrical, mechanical)
  • Draining and filling systems
  • Daily and weekly operator checks
  • Instruction manuals

Our Integrated Approach

Our Commissioning and Project teams are involved at the point of Sales handover. During Project Progression, the Commissioning Manager, together with the Design and Project Teams, produce a dedicated Commissioning Documentation package to suit the individual project installation and meet your strategic requirements.

This includes:

  • Risk Assessment and Method Statement (RAMS) and procedures
  • Commissioning checklist and documentation
  • Inspection and Test Plan
  • Full supporting document package

Artboard 5

Talk To One Of Our Team About Our Power Plant Commissioning Services

For more information about our Installed Energy Solutions for Gas Power Generation, please get in touch.

Get in touch now